Agenda Bill Report
File Number: AB2023-651
File ID: AB2023-651 Version: 1 Status: Adopted
File Created: 09/27/2023 Entered by: LCumming@co.whatcom.wa.us
Department: Public Works File Type: Ordinance
Department
Assigned to: Council Finance and Administrative Services Committee Final Action: 10/24/2023
Agenda Date: 10/24/2023 Enactment M ORD
2023-060
Related Files:
Primary Contact Email: sdraper@co.whatcom.wa.us
TITLE FOR AGENDA ITEM:
Ordinance amending the project budget for the E. Smith/Hannegan Road Intersection
Improvements Fund, Request No. 3
SUMMARY STATEMENT OR LEGAL NOTICE LANGUAGE:
See memo
HISTORY OF LEGISLATIVE FILE
Date: Acting Body:
Action:
Sent To:
10/10/2023 Council INTRODUCED Council Finance and
Administrative Services
Committee
Aye: 7 Buchanan, Byrd, Donovan, Elenbaas, Frazey, Galloway, and Kershner
Nay: 0
10/24/2023 Council Finance and Administrative RECOMMENDED FOR
Services Committee ADOPTION
Aye: 3 Donovan, Frazey, and Kershner
Nay: 0
10/24/2023 Council ADOPTED
Aye: 7 Buchanan, Byrd, Donovan, Elenbaas, Frazey, Galloway, and Kershner
Nay: 0
Whatcom County Page 1 Printed on 1012512023
Agenda Bill Report Continued (AB2023-651)
Attachments: Proposed Ordinance, Memo To Council UPDATED on 10.5.2023
Whatcom County Page 2 Printed on 1012512023
1
2 PROPOSED BY: Public Works
3 INTRODUCTION DATE: 10/10/2023
4
5
6 ORDINANCE NO. 2023 - 060
7
8
9 ORDINANCE AMENDING THE PROJECT BUDGET FOR THE E.
10 SMITH/HANNEGAN ROAD INTERSECTION IMPROVEMENTS FUND,
11 REQUEST NO. 3
12
13 WHEREAS, Ordinance No. 2018-057 established the E. Smith/Hannegan
14 Road Intersection Improvements Fund in 2018 granting expenditure authority to
15 initiate preliminary engineering for the multi -year project, and;
16
17 WHEREAS, previous phases of the project included preliminary engineering,
18 permitting, property rights acquisition, construction and construction engineering
19 services, and;
20
21 WHEREAS, it is now necessary to supplement the project -based budget with
22 additional funds for the preliminary engineering, right-of-way, and the construction
23 phases, in order to complete the design and construct the project, and;
24
25 WHEREAS, the East Smith & Hannegan Road Intersection Improvements
26 Project was confirmed on the Council approved 2023 Annual Construction Program
27 and is item number R6 on the Council approved 2023-2028 Six Year Transportation
28 Improvement Program (2023-2028 STIP), and;
29
30 WHEREAS, the original construction cost and property rights acquisition cost
31 estimates have increased due to economic changes in market forces along with
32 necessary design changes, and therefore the 2023-2028 STIP estimate of $5.8
33 million is insufficient, and;
34
35 WHEREAS, the project previously secured $2 million of outside funding
36 commitments ($1 million federal Highway Safety Improvement Program funds and
37 $1 million federal Surface Transportation Block Grant funds), as well as $3.8 million
38 of local Road funding, and;
39
40 WHEREAS, the project has secured an additional $1,952,642 of outside
41 funding commitments ($1.5 million federal Surface Transportation Block Grant
42 funds and $452,642 federal Carbon Reduction Program funds), as well as $222,358
43 of local Road funding, and;
44
45
Page 1
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
NOW, THEREFORE, BE IT ORDAINED by the Whatcom County Council that
Ordinance No. 2018-057, associated with establishing a project -based budget for
the E. Smith/Hannegan Rd Intersection Improvements Fund, is hereby amended,
effective October 24, 2023 by adding an additional amount of $2,175,000 of
expenditure authority to the project budget for a new current project budget
expenditure amount of $7,975,000 as described in Exhibit "A"
®;e49[f931d1iJ
P i � day of October , 2023.
M1 1 d ?
o
�� WHATCOM COUNTY COUNCIL
,Al'fF�T `� 00A ATCOM XC0J,',rW�kSHINGTON
Dag a rows, D vis;,,CJerPc of the Council Bar clizinaff,Chair of the Council
APPROVED AS TO FORM:
hristopher Qbinn
Senior Civil Deputy Wsng Attorney
Page 2
( Approved ( ) Denied
Date Signed: rat
Exhibit "A"
Project Based Budget - Budget Request Tracking Sheet
Project Title: E. Smith Road & Hannegan Road Intersection Improvements
Project Codes: CRP No. 914002; Cost Center 382100
Project Based Budget Request: No. 3
Duration Requested: 3 yrs (2023, 2024, 2025)
Current
Amended
New
Budget Account
Project Activity
Approved
Project
Approved
Project
Budget
Project
Budget
Request
Budget
595110 Preliminary Engineering (In -House & Consultant) $750,000 $200,000 $950,000
595200 Right of Way $550,000 $225,000 $775,000
595300 Construction $4,000,000 $1,750,000 $5,750,000
595120 Construction Engineering (In -House & Consultant) $500,000 $500,000
TOTAL $5,800,000 $2,175,000 $7,975,000
Current
Amended
New
Object Account
Project Funding
Approved
Project
Approved
Project
Revenue
Project
Revenue
Request
Revenue
8301 Local Funds (transfer from Road Fund)
4333 Federal STBG Funds (Reimbursement for construction)*
4333 Federal HSIP Funds (Reimbursement for construction)*
4333 Federal CRP Funds (Reimbursement for construction)*
*HSIP = Highway Safety Improvement Program
*STBG = Surface Transportation Block Grant
*CRP = Carbon Reduction Program
$3,800,000 $222,358 $4,022,358
$1,000,000 $1,500,000 $2,500,000
$1,000, 000 $1, 000,000
$452,642 $452,642
TOTAL $5,800,000 $2,175,000 $7,975,000
Supplemental Budget Request
Public Works Administration
Supp'i ira # 4365 1 Fund 382 Cost Center 382100 Originator. Julia Green
Expenditure Type: One -Time Year 1 2023 Add'I FTE ❑ Add'I Space ❑ Priority
Name of Request. Fund 382 E. Smith/Hannegan Intersection Imp. Amd 3
X
Department Head Signature (Required on Hard Copy Submission) Date
Costs:
_Object
Object Description _
Amount Requested
4333.2022
STP (Surface Trans Prog
($1,500,000)
4333.2029
FHWA-Other
($452,642)
6110
Regular Salaries & Wages
$36,000
6290
Applied Benefits
$24,000
—
6630
- --- ---- — --
Professional Services
..._..----------
$20,000
_......._..
6630
--------_.._..
Professional Services
---
$140,000
7320
Land
$205,000
7380
Other Improvements
$1,750,000
8301
Operating Transfer In
($222,358)
Request Total
$0
1a. Description of request:
The intersection of E. Smith and Hannegan Roads is located in Sections 28, 29, 32, 33, T39N, R3E and
experiences delays due to lack of left -turn channelization on Smith Road. The project is listed as #R6 on
the 2023-2028 Six -Year Transportation Improvement Program. An alternatives analysis was completed by
a consultant, that reviewed traffic counts and warrants. It was determined that a multi -lane roundabout
was the preferred improvements. Construction is scheduled for summer 2024. This request provides the
funding needed in the project based budget to complete the preliminary engineering and right-of-way
phases of the project, along with enough funding to advertise and award a construction contract.
1b. Primary customers:
All road users who travel on the Hannegan and Smith Road corridors.
2. Problem to be solved.
The main purpose of the intersection improvements is to improve vehicle operations and increase safety
for vehicle drivers, bicyclists, and pedestrians.
3a. Options /Advantages:
The alternatives analysis completed in 2018 compared three alternatives for improvements to the
intersection. The three alternatives were an upgraded traffic signal with protected left turn movements, a
single -lane roundabout, and a double -lane roundabout. The double -lane roundabout provided the highest
level of vehicle operations for a twenty year design life, while providing a much safer intersection than the
existing signal or an upgraded signal.
3b. Cost savings:
Potential costs savings are realized by an improved level of service for the motoring public and potential
decrease in motor vehicle accidents.
4a. Outcomes:
The approval of budget authority will allow for the completion of design, RM acquisition, permitting, and
construction of the chosen alternative.
Monday, September 25, 2023 Rpt Rpt Suppl Regular
Supplemental Budget Request
Public Works Administration
supp 1 ir) f+ 4365 I Fund 382 Cost Center 382100 Originator: Julia Green
4b. Measures:
The measures of success will be the obligation of construction grant funds of $3,952,642 when R/W is
certified and environmental permits are signed off by FHWA and WSDOT
5a. Other Departments/Agencies:
n/a
5b. Name the person in charge of implementation and what they are responsible for:
n/a
6. Funding Source:
The construction contract and in-house construction engineering work will be funded with Surface
Transportation block Grant (STBG), Carbon Reduction Program (CRP), and Highway Safety Improvement
Program (HSIP) funds. The remainder of the project will be covered with local road funds.
Current Funding:
Federal STBG: $1,000,000
Federal HSIP: $1,000,000
Road Funds: $3,800,000
Proposed Additional Funding:
Federal STBG: $1,500,000
Federal CRP: $452,642
Road Funds: $222,358
Total Project Budget: $7,975,000