TITLE OF DO NT: Amendment No.] to Ordinance No. 2014 -083 Establishing the Cedar Hills/Euclid
Storm Water Improvements Fund and Establishing a Project Based Budget for Cedar Hills/Euclid Storm
Water Improvements
ATTACHMENTS: Ordinance Amendment, Exhibit A, Supplemental Budget Request, and Memorandum
SEPA review required? ( ) Yes ( X ) NO Should Clerk schedule a hearing? ( ) Yes ( X) NO
SEPA review completed? ( ) Yes ( X ) NO Requested Date:
SUMMARY STATEMENT OR LEGAL NOTICE LANGUAGE. (If this item is an ordinance or requires a public
hearing, you must provide the language for use in the required public notice. Be specific and cite RCW or WCC as appropriate.
Be clear in explaining the intent of the action.)
Amendment No I to the Cedar Hills/Euclid Storm Water Improvements Fund Project Budget requests
additional appropriation authority of $665,586 for a new Project Based Budget total of $1,295,586.
COMMITTEE ACTION:
4/19/2016: Forwarded to Council for adoption
COUNCIL ACTION.•
4/5/2016: Introduced 7 -0
4/19/2016: Adopted 7 -0, Ord. 2016 -014
Related County Contract #: I Related File Numbers:
Ordinance or Resolution
Number: Ord. 2016 -014
PROPOSED BY: Executive
INTRODUCTION DATE: _April 5, 2016
ORDINANCE NO. 2016 -014
AMENDMENT NO. 1 TO ORDINANCE NO. 2014 -083 ESTABLISHING THE CEDAR
HILLS /EUCLID STORM WATER IMPROVEMENTS FUND AND ESTABLISHING A
PROJECT BASED BUDGET FOR CEDAR HILLS/EUCLID STORM WATER
IMPROVEMENTS
WHEREAS, the Lake Whatcom Comprehensive Stormwater Management Plan
identified the Cedar Hills /Euclid Natural Drainage Retrofit as a high priority capital
improvement project, and
WHEREAS, design work is currently underway for this project through a contract with
Wilson Engineering, and
WHEREAS, the Stormwater Division was successful in obtaining a Combined Water
Quality Financial Assistance grant from the Department of Ecology to aid in funding the
design and construction of this stormwater retrofit, and
WHEREAS, this Ecology funding, in addition to the allocated REET II funding, will allow
for the expansion of the scope of work to maximize the water quality benefit by
constructing additional stormwater facilities and including a channel stabilization
element as part of the project, and
WHEREAS, the budget expenditure authority for the Ecology funding is now being
requested in this project -based budget fund,
NOW THEREFORE BE IT ORDAINED by the Whatcom County Council that Ordinance
No. 2014 -083 is hereby amended adding $665,586 of expenditure authority, as
described in Exhibit A, to the original project budget of $630,000, for a total amended
project bud% safe$1,g95,586.
}� ,
� �! 6 illls' 9 b day Of April , 2016.
4 f
Go
. °� u•; = WHATCOM COUNTY COUNCIL
ATI: a WHATCOM COUNTY, SHINGTON
Dana Brown-'9419, nci ler *Lan'Chair of the Council
lilt
APPROVED AS TO FORM: I( AvprovedA () Denied
EXHIBIT A
CEDAR HILLS /EUCLID STORMWATER IMPROVEMENTS
Project Budget Current project budget Amendment #1 Total Amended
Expenditures Account Description Ord. 2014 -083_ to Ord. 2014 -083 Project Budget
7380 Other Improvements $630,000.00 $665,586.00 $1,295,586.00
Revenues
4334.0311 Dept of Ecology Grant $0.00
$665,586.00
$665,586.00
8301.169 Flood Fund Transfer $10,000.00
$0.00
$10,000.00
8301.324 REET II Transfer $620,000.00
$0.00
$620,000.00
$630,000.00
$665,586.00
$1,295,586.00