HomeMy WebLinkAboutSurface Water Work Session October 18 20051
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
Whatcom County Council
Special Surface Water Work Session
October 18, 2005
Council Chair Laurie Caskey- Schreiber called the meeting to order at 10:00
a.m. in the Whatcom County Civic Center Annex, Second Floor Meeting Room, 322
N. Commercial, Bellingham, Washington.
Present:
Barbara Brenner
Dan McShane
Seth Fleetwood
Sharon Roy
L. Ward Nelson
Absent:
Sam Crawford
SURFACE WATER WORK SESSION (AB2005 -025)
Bruce Roll, Assistant Director, stated he submitted information on recycled
electronics (on file) that the Council requested. There is a hotline the County funds
that answers the phone during business hours. That's where to call to find out how
to recycle things.
1. SALMON RECOVERY
South Fork and Canyon Creek Grants Applications
John Thompson, Senior Planner, stated a memo in the packet is regarding
the Salmon Recovery Funding (SRF) Board applications. Short project descriptions
are attached. The Canyon Creek assessment and design project is to do sufficient
assessment work to get actual designs prepared so they are able to identify what
they can do and what financial resources are needed. The second project is the
East Acme Farm community restoration project. The Council is aware of the
project. It works in tandem with the Lummi Nation and Nooksack Tribe to put
logjams on the lower section of Hutchison Creek to improve fish habitat and meet
concerns from the community. Both applications were submitted at the end of
September through the local entity. Canyon Creek ranked number four out of five
and the East Acme Farm ranked number three out of five. The State board will
make a funding decision the first of January 2006.
McShane asked if there was work at Canyon Creek this summer. Thompson
stated there was not. They had to go through the U.S. Fish and Wildlife Service
and the National Oceanic and Atmospheric Administration (NOAA) Fisheries Division
Surface Water Work Session, 10/18/2005, Page 1
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
for project design. However, the project was permitted after the fish began
spawning. The resource agencies were not comfortable with them working in the
water while the fish were spawning. The permits are in hand for next summer.
The work is to install bedrock weirs at that spot. Relocating the channel is a major
design and engineering project and requires a higher test of whether the agencies
would buy off on it.
Roll stated relocating is proposed.
McShane asked if staff submitted the alluvial fan study they had done. He
asked if follow up work includes a study to know what is currently occurring on the
fan. Thompson stated the fan study will provide specific restoration
recommendations and designs. It provides good background information that
allows them to prepare designs.
McShane asked about the East Acme farm. There have been some concerns
about the Tribal project. The County Council has no authority over the project. He
asked if the Executive approved the project. Thompson stated it is pending the
outcome of this process.
Roll stated it is held up because of the SRF Board, not the County. The SRF
Board said it will not allow them to do any more work.
Thompson stated the SRF Board gave two reasons in its letter to the Lummi
Nation. Their first concern was about the community concerns. The biggest
concern is the Lummi proposed amendment to the grant agreement to significantly
reduce the physical scope of the project, but the same amount of money would be
spent. The original proposal was to remove 6,000 linear feet of rock. Practically,
they found they weren't able to do that. Also, analysis indicated they weren't ready
to do that. When installing large logjams, costs go up.
Roll stated his goal is a project to expand that, address community concerns,
and expand the Lummi project. The expanded portion is in the grant. He hopes
both projects move forward next year.
Brenner asked if negotiations between the County and Lummis would resolve
the issue. Thompson stated it doesn't resolve the issue for SRF Board about the
scope of the project.
Brenner asked if anyone tried to work with the Lummis to resolve that
change in the scope. Thompson stated that is an issue for the Lummis. Their
amendment is with the state SRF Board, not the County.
Brenner stated she thought the County may be able to help negotiate it the
way it was.
Surface Water Work Session, 10/18/2005, Page 2
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
Roll stated the reason they're up there is because of community concerns
that weren't addressed with the original project. The County spent six to eight
months working with the community to allow the Lummi project to move forward.
They have teen talking with the SRF Board on what the County desires for both
projects.
Brenner stated it seems like they get things moving, and then there isn't
enough communication with the Lummis about what is going on. Work with the
Lummis to get these things resolved in a timely fashion. Cooper stated they will
work with them on the cultural aspect.
Thompson stated the County met with both tribes early on regarding the East
Acme Farm project.
Roll stated both the Lummis and the County are interested in getting the
project going.
Nelson asked about the woody debris technique being used. He asked for
examples of where woody debris has stabilized existing logjams and encouraged
new wood in meandering rivers. Thompson stated there are examples. He would
find the information.
Nelson stated he is concerned about spending money when there may be
future problems. While salmon is important, flood control money is for public
safety, not fish habitat.
Roll stated a lot of the jams are beefed up so they can withstand serious
events. There is an aspect to get back to properly functioning conditions and
addressing flood needs. When a flood project is proposed, look at what meets the
needs of the flood and also the potential gain of the salmon recovery plan. The
topic that they'll need to address as they move forward in the salmon recovery plan
is the potential risks that will result as they put in more logjams.
Chris Hatch, Flood Control Zone District Advisory Committee, stated the
scope of what the Lummis proposed at the East Acme Park still wasn't acceptable to
the community. It required a County reaction. The idea is that the County project
will mitigate the community concerns that the Lummi project wasn't able to
address.
McShane asked how the Nooksack Tribe and Lummi Tribe feel about this
change to the East Acme Farm project. He hasn't heard from them directly.
Thompson stated that in response to community concerns, the Lummis redesigned
their project. He's heard their design meets the habitat objectives. In order to
deal with evulsion risk through the old Hutchison channel, they are using as much
wood and other materials as they would for two or three other logjams that could
be placed along the river. To address the flood concerns more fully, they give up
two or three habitat structures in the river.
Surface Water Work Session, 10/18/2005, Page 3
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
McShane asked if the main change is on preventing an evulsion on Hutchison
Creek. Thompson stated it is that, and also beefing up the structures in the river.
The structures are big logjams of the size that were there historically. Lummi is
proposing a different logjam design that is more in the breadth of the flow. They
are highly engineered structures to withstand a 100 -year flood.
Salmon Recovery Plan Implementation
Thompson submitted handouts (on file). He submitted a draft plan at end of
June to Shared Strategy, which submitted a package to the NOAA Fisheries
Division. Now, they are waiting for some feedback from federal services to see
what they think of the County's portion of the plan. They are in the mode now to
begin or continue to implement identified actions in the plan. The handout is from
the executive summary. He read through the handout on the eight key actions and
the County's involvement for each.
Action one is looking at the big Chinook passage issues. There are two
pieces, the Middle Fork water diversion and Canyon Creek. For the Middle Fork, the
County involvement is limited to monitoring instream flows. For Canyon Creek, a
high priority is to deal with the overall quality of the habitat and also to deal with
the bedrock outcrop barrier. The quality hasn't recovered well from the 1989 and
1990 flood events.
Caskey- Schreiber asked if the barrier is the temporary levee. Thompson
stated it is not the levee. When they did the work in 1994 to install the levee,
there was an outcrop of sandstone on the left bank that they drilled to put the
channel through. Both upstream and downstream, the beds were lower. It initially
wasn't a problem for fish. However, now the steps are too big for the fish since the
sediment moved out. Depending on which way the boulders move each winter,
they may not be able to get fish through it.
McShane stated the channel needs to be moved, in his opinion. They can't
run through that bedrock. The fan is dynamic. The sediment load is reduced for
the time being. It's only going to get worse and worse. Don't make this too
complicated. There will always be problems in the watershed due to landslides.
The damage throughout the Nooksack habitat region is a key component. Be
aggressive about getting this thing taken care of. It's been identified since 1995.
It's only gotten worse. It's changed significantly in the last few years. Thompson
stated they will consider relocating the channel, but they must also (inaudible).
McShane stated the sediment regime is completely different from what it was
in 1989. Thompson stated they are now looking at the aftermath of catastrophic
events. Those are all things they need to look at to come up with a plan that will
be durable through another event like the one in 1989.
Surface Water Work Session, 10/18/2005, Page 4
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
Brenner asked if another option is scalping. Thompson stated the lower area
of the creek is moving out more sediment than is coming in. So, taking out gravel
wouldn't be as important as giving the channel a shape and gradient to make it
more self- maintaining.
McShane stated the channel is incising deep into the fan. He's not sure they
should go after a hard long term fix because it is so dynamic. They may be back to
having the whole fan buried in rubble. Thompson stated key considerations are
what to do, what it will cost, and how long it will last.
McShane stated assume it's not going to last long.
Nelson stated a huge amount of runoff is due to the gradient. The question
is how broad a fan is necessary to make it protective. Thompson stated that is a
question. Another issue is the flood hazard and risk. From a fish perspective, there
are things to do that may or may not address the flood risk perspective. Keep in
mind both flood and fish at the same time. Keep in mind the catastrophic events.
The results can be damaging.
Nelson stated the buyout program is to prepare for a catastrophic event.
Thompson stated the question is whether to let the dike fail catastrophically,
systematically repair it, or dismantle and relocate it.
Caskey- Schreiber asked how big was the 1989 or 1990 event.
Paula Cooper, River and Flood Division Manager, stated it was a 200 -year
debris flow event. Debris flows tend to be two to five times bigger than normal
flood events.
Thompson stated actions two and three go together. Integrate salmon
recovery with flood projects. The focus is to ferret out what Chinook and other
salmon need in the main stem and other major forks and tributaries. They have
ideas. Now, they need to identify the low- hanging fruit to work on, then refine
their knowledge of the areas with the greatest restoration potential. Through the
flood plan, they know where key and recurrent flood problems are.
Nelson stated the costs of items two and three are close to $100 million. He
asked what timeliness means. Thompson stated the numbers are not real solid.
They need to be refined. These timelines are for the next ten years.
Roll stated the current financial strategy being proposed by the Salmon
Recovery (SRF) board is approximately $40 million over ten years. Those are
federal and SRF Board monies. The current proposal would double or triple the
amount coming in now. They are prioritizing different drainages. Now that there is
an entire Puget Sound plan, they are prioritizing the areas in the Puget Sound.
They propose to realign how existing funding is distributed. The goal is to get as
many of the actions done in the ten years as possible. This isn't going to require
Surface Water Work Session, 10/18/2005, Page 5
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
new funding. This will use things such as mitigation and existing opportunities.
The State is also looking at diverting mitigation monies from large projects such as
the Guide Meridian project and Seattle area projects.
Fleetwood asked if it's not anticipated that Whatcom County will have to
appropriate significantly more money in the next ten years. Roll stated that's not
what he said. The Puget Sound plan anticipates that the basin will receive about
$40 million over ten years for salmon recovery efforts, but it does not propose that
communities come up with new funding. It proposes that communities redirect
existing funding.
Jeff Monsen, Public Works Director, stated there is a lot of optimism out
there that plans like this will be implemented. To insure that the plan is done, then
generate new local money. An alternative is to use the current revenue stream and
change the sequence of activities. Those are budget neutral, but not policy neutral.
Caskey- Schreiber asked if the Public Works Department will put that ranking
forward to the Council. Monsen stated they will try, more so from the River and
Flood Division and not so much from the Road Division. At this table, begin to look
at where to focus the resources to get the biggest benefit, dealing with natural
resource, river and flood, and transportation issues. Define a strategy to move
toward the same vision. That may require a change in course from what they've
done historically, but having the discussion will let them put the full picture on the
table.
Brenner asked if this has two functions, salmon habitat restoration and flood
control. She asked if they can use flood money for salmon habitat restoration.
Monsen stated the road, flood, and general funds are all available to implement
elements of this. However, be careful they don't deplete financial capacity to do
other things as well.
Thompson stated the fourth action item is the critical areas and shoreline
updates. They have made sure the salmon recovery plan information was available
as they developed those updates. The critical areas ordinance update is complete.
The shorelines update is in the works.
Action five is instream flows. They are working with the Bertrand Creek
instream flow pilot project and the Middle Fork instream flow pilot project.
Establish a clear methodology and process for addressing instream flows
throughout the basin.
Action item six is the nearshore estuary. When looking at the current
strategy used to review SRF Board projects, it says estuary and near shore areas
are very important. They haven't detailed which is more important or why. This
ties to the shoreline plan update and with the Marine Resources Committee to
identify the areas that are working well and the areas that are degraded, the
restoration opportunities, and where to get the most benefit from restoration.
Surface Water Work Session, 10/18/2005, Page 6
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
Action seven is the lowland and tributaries. Those areas receive lower
priority because they are not used by early Chinook, yet they are significant to
other species such as bull trout. This is a place where the County has an important
role. The County is completing the culvert inventory. They are coming up with
specific designs and priorities for sites to be repaired on private land. The six -year
transportation planning process ties into the stormwater program. It also ties into
the Conservation District for farm plan development.
McShane asked about action six. He asked that it be tied to action seven.
Stormwater management is to minimize negative impacts on habitat. That could be
added, even if it may be duplicative, to the nearshore estuary habitat issue. They
are starting to gain an understanding of the impacts to the nearshore habitat from
stormwater runoff. Even clean runoff can be a real detriment to the juvenile fish.
He is concerned they aren't prepared to have an appropriate stormwater plan for
residential development and its interaction with the nearshore habitat.
Roy asked if Councilmember McShane is suggesting that stormwater issues
be addressed in both action items six and seven. She agrees with that.
Thompson stated Birch Bay planning is a good place to insert that initially.
The last action is one in which the County is not directly involved. The
salmon co- managers are considering a program to use the Skookum Creek
hatchery to supplement those populations.
Nelson stated many actions that will take a lot on the County's part. A
concern is the measurement of outcomes. Roll stated the financial plan recognizes
that 10 or 15 percent of every project would have to have a long -term monitoring
commitment. Of that $40 million, at least 10 percent is used specifically for
monitoring and reporting results.
Thompson stated the validity is whether they are getting more fish back.
Nelson stated they won't know which measure gets the fish back. Thompson
stated that's part of the challenge of management. That's why a detailed adaptive
management plan is in the works. They have to answer those questions on local
and State levels.
Roll stated it takes time to undo 150 years of damage.
(Clerk's Note: End of tape one, side A.)
Roll continued to state that it is not only a challenge to bring the plan
forward, but to get the community culture to understand it's important.
Surface Water Work Session, 10/18/2005, Page 7
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
Nelson stated they hope to see effects at the end of the ten years given the
lifecycles. They also want to see how the fish respond to the specific actions, such
as if they are using the riparian habitat and if they are using the instream flow.
Thompson stated monitoring needs to fit the functions. The question must fit the
project. A lot these physical systems may take substantially longer than the
lifecycle of the salmon. It will take a while for the systems to settle down. People
tend to think in timeframes of two -year or six -year legislative cycles, when they get
federal funding. That doesn't really fit the fish or the landscape. Their initial
funding for SRF Board was five years. Now they are asking for evidence of
increased fish populations. People are trying to educate them that it takes longer
than that to see results.
that.
Brenner asked if there are still a bunch of nets in the river.
Nelson stated that is in the lower portion, but the Lummis have a right to
Roy stated the Lummis have a right, but only at a certain time in the cycle.
Thompson stated the Lummi net fishery fishes from Slater Road downstream.
They don't open the season until the critical stock of spring Chinook are through the
system. The nets are not there all year long. Some derelict nets come into the
system, but that is a separate issue.
2. RIVER AND FLOOD ISSUES
Flood Project Mitigation Strategies
Paula Cooper, Flood Division Manager, stated there are two subcommittees of
the Flood Control Zone District Advisory Committee. One is a Management and
Oversight Subcommittee. The second is the Gravel and Sediment Subcommittee.
The first discussion is about amount of mitigation they incorporate into the
flood projects. With the Everson overflow project, the cost of mitigation was about
40 percent of the project cost.
Art Anderson, Flood Control Zone District Advisory Committee Member,
stated it's a good idea to share things with the County Council. Have some mindful
thinking and skillful discussion on this issue. He is not against fish, but the
question is how much is enough for mitigation. Recently, the Army Corps of
Engineers figure five percent for mitigation. He asked the Council to establish a
reasonable limit of money spent in each project for mitigation. The advisory
committee's basic scope of work is to protect lives and infrastructure.
Caskey- Schreiber asked for more information on the mitigation fees and how
they assess fees.
Surface Water Work Session, 10/18/2005, Page 8
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
Cooper stated mitigation is negotiated through the permit process. A goal is
to lessen the project impact. For the Everson overflow project, the mitigation need
was raised because of the length of the project. They had to mitigate for the rock
that doesn't provide habitat as good as wood, and they also had to provide for lost
opportunity of the river to migrate and create fish habitat. Through the process of
negotiating with the permitting agencies, the agencies proposed initial mitigation.
Some of the mitigation requests, from the tribes and Fisheries, were impossible to
do.
Jeff Monsen, Public Works Director, stated a straight definition of mitigation
is difficult. The process of coming up with mitigation is new every time. Mitigation
means no net harm, per the State of Washington. To get over the hurdle of the
negotiation process and in looking at plans, the agreement with State Department
of Fish and Wildlife is to state the agency's minimum requirement, and then the
County will agree to do a little more with the minimum. There is no real target for
mitigation in legislation. Some entities have set a financial limit, which sometimes
kills a project. The conflict in a lot of these projects is that, according to the
Endangered Species Act (ESA), someone is supposed to be restoring the fishery.
Under a permit however, there is no obligation to restore, only to mitigate. The
tribes expect that someone is going to restore the fishery, so that's the position
they take. They have a right to that expectation. They won't engage the County of
restoration versus mitigation.
Nelson asked if an example is that the federal government will issue a no go
if the cost of mitigation exceeds an agreed upon financial limit for mitigation.
Monsen stated that if the County sets a financial limit, there may be projects that
cross that limit and the County won't pursue them because they can't get
permission to do them at the mitigation level the County has pre- approved.
Federal agencies reaction is unknown. There is no boundary as far as what they
can ask for.
Nelson asked if the advisory committee was uncomfortable with the
mitigation cost being 40 percent of the entire project.
Jeff Chalfant, Senior Planner, stated mitigation at best is defined as no net
loss of ecological functions. There is a Constitutional issue. The County can't
require someone to mitigate to restoration. The County can only require someone
to mitigate for impacts directly related to the project. They can't ask for more.
From an agency perspective, no one can ask for restoration. The tribes may be
able to negotiate for more in the process, but the State and federal agencies can't
ask for more.
Monsen stated they do ask for more, but can't require it.
Roy asked for an estimate of how many times the County meets the
minimum standards versus going over into restoration for every flood project or
road project that might affect habitat and fish. She asked where they are with the
Surface Water Work Session, 10/18/2005, Page 9
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
minimum no net loss versus restoration. Monsen stated it is rare that the County
does only the minimum. The reason is because of how long they want to delay
work trying to come to the legal definition of what the minimum is.
Fred Polinder, Flood Control Zone District Advisory Committee Member,
stated that after the flood in the 1990's, the Council established the flood tax. This
summer, they agonized over approval of two projects. Forty percent on some of
these projects is for fish, not flood control. His committee is to take care of
damage from floods. Some requirements are totally ridiculous and are not even
getting done. The mitigation can be unbelievable. Fisheries waits until the County
is in dire straits to get things done.
McShane asked if the 40 percent mitigation for the Everson project was
recommended by the advisory committee. Anderson stated the advisory committee
felt that 40 percent was above and beyond what was necessary. He disagrees with
Mr. Monsen about giving more to the agencies than they ask for. It's gone so far
one way that it's time to swing back. If the taxpayers of Whatcom County knew
the value they're getting for their tax dollars, they would be up in arms.
McShane asked if the Flood Control Zone District Advisory Committee
recommended the project. Anderson stated it did not at first, and then did at a
later date.
McShane asked if the main issue is the cost of the mitigation. Anderson
stated the cost of the design is the main issue. He approved it because it is the
main corridor to go to Sumas. He felt uncomfortable approving it.
McShane stated they go through a permitting process that is unclear. He
understands the requirement for the nexus with the project. He asked if clarity
must be achieved through a process other than a permit process, using the court
process. Monsen stated that is possible. When he talked about doing more than
the minimum, it is at the State regulatory level. They apply that standard when
they deal with the North Lynden drainage work. When it comes to a river project
and federal issues, he has not made that commitment.
They may need to define a limit, especially with the decline in the federal
money going to the response to the ESA and Clean Water Act. The resource
agencies grab a hold of a locally sponsored project to make up the difference. They
are not allowed to do their own restoration projects. On the State and federal
levels, he has tried to focus on the minimum requirement and then put the
arguable amount of money toward where it is really the highest salmon priority.
The permitting process is the magnet for restoration. The salmon plan tried to
redirect where those resources go to.
McShane stated he may be interested in going down that road, but not on all
projects. There may be costs that aren't worth it. If it's the right kind of project
Surface Water Work Session, 10/18/2005, Page 10
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
where the mitigation seems absurd, it might not take a lot of studies to
demonstrate that. He doesn't know if the Everson project is one of those.
Nelson stated separate the funding mechanism for projects that have a
mitigation impact more than the minimum. He asked if they've discussed it.
Monsen stated they have somewhat. It's a matter of applying tools to make that
happen. One tool is mitigation banking. Formalizing those relationships is difficult
to do. In some cases, there are conflicting goals.
Nelson stated pursue that before making a decision.
Caskey- Schreiber stated the critical areas ordinance asks for a mitigation
banking program.
Brenner asked at what point it is mitigation and not restoration. Forty
percent mitigation is really restoration. They will soon need to negotiate a formula
with the tribes and agencies. She asked how they can use flood money for
restoration. Monsen stated that from a legal standpoint, the formation of a flood
district has broad powers on which to spend money. The money can be used for
salmon restoration. Focus on where resources are going so they don't deplete
capacity to do projects that are a priority.
Polinder stated they agonized over the Everson project. It wasn't a lot of
money, but it was the principle. The fish mitigation required was ridiculous.
Everson was being blackmailed. If they didn't go through with it, there would have
been penalties. Serving on this committee is getting disgusting with the blackmail
they're getting on these projects.
Cooper stated the County didn't negotiate that mitigation.
Chris Hatch, Flood Control Zone District Advisory Committee Member, asked
who defines net loss in the negotiations.
Chalfant stated achieving no net loss is challenging. That's why some
agencies ask for more, because they don't know the impact of the project. It's a
way of expediting permit review and issuance. They will agree to do more that
they know will cover the impacts of the project, not knowing the exact loss. The
definition of loss is anything that drops below the baseline of fish conditions.
McShane stated that measuring the dip below the baseline is difficult and
expensive. He asked if they are talking about a full -blown environmental impact
statement (EIS) before each project. Monsen stated that the ESA has a no net loss
standard view. If someone is going to commit a take by killing one fish, even if the
intent is to put four fish back, that person has to prove that will happen first.
Roy stated it sounds like an argument can be made that, when confronted
with the no net loss issue, it's less expensive just to say they will go a little bit
Surface Water Work Session, 10/18/2005, Page 11
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
above the baseline rather than go to the expense to measure the loss. It's an
economic decision more than a mitigation level decision.
Brenner stated it seems like, to expedite something that protects people
from floods, mitigation is more expensive. Have some kind of negotiated
percentage that they won't go above.
Caskey- Schreiber stated that is contrary to what Mr. Chalfant said. They are
bound to mitigate the project impacts. You never know what those impacts will be.
Nelson stated set aside a certain amount of funding in total to be used for
mitigation on all projects. Monsen stated there are legal issues in doing that. They
must mitigate the impacts. An agency can't approve a project that doesn't address
mitigation.
Nelson stated this gives agencies monies to do projects. Monsen stated
they've put that concept on the table. However, it's not easily accomplished.
Ron Bronsema, Flood Control Zone District Advisory Committee Member,
stated it ties into their cooperation with the Army Corps of Engineers. The advisory
committee is frustrated with the Corps' stream bank restoration. They waste a lot
of valuable County staff time trying to get permits to do projects that the Corps can
do and on mitigation. They can better use staff working on the hydraulic model and
other things identified in the Comprehensive Plan. They're still working on the
model on reach three. They approved the Comprehensive Plan six years ago. He
asked how they can justify spending all this staff time trying to get permits. The
problem is not just with the high mitigation costs.
Brenner stated they are always on the defense. She asked why the County
can't say that the agencies have to prove that their proposed mitigation won't
compensate for the loss.
Chalfant stated when securing a permit, the burden of proof is on the
applicant to show the project doesn't have impacts. Also, when trying to secure
Corps permits, the federal government has a trust relationship with the tribes. The
federal government is responsible for making sure their treaty rights aren't
affected. If there is an impact to resources, they must meet a de minimus test.
Caskey- Schreiber stated they've heard that slows down the permit process.
Nelson asked who is liable if an applicant is denied a permit to take down a
dangerous tree, and the tree falls on a house. Chalfant stated the County planning
department could potentially have liability.
Nelson asked who is liable if a flood wipes out Everson, if the County isn't
allowed to build the projects needed to protect Everson. Chalfant stated there is
Surface Water Work Session, 10/18/2005, Page 12
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
exposure for the agencies. An attorney could answer that question. When there
are emergencies, permits come rather quickly.
Cooper stated the County has done two emergency projects in Everson and is
working on a third. They have agreed to do mitigation later.
Anderson stated the committee has articulated its concerns. It needs advice
from the Council. Now, the Army Corps of Engineers is doing the heavy lifting for
Whatcom County. Be less defensive and more offensive. When projects are held
over to the following year, they become more expensive. Think about this and give
the committee guidelines about what would be an appropriate level.
Brenner stated it seems that if they go ahead and issue a blank check, the
County can still show information on what the mitigation should be. She asked if
they have to show why the County's proof isn't adequate. The County should
provide its proof and make the agency prove the County's proof is wrong.
Roy stated the agencies have the power of the permit. That is the pathway
to court, which the County may need to take.
Hatch stated don't be surprised if there is a project that the Flood Advisory
Committee doesn't approve because the mitigation is more than an amount that is
a good use of money.
(Clerk's Note: End of tape one, side 8.)
McShane stated the Council can discuss what guidance it wants to give to the
advisory committee on the percent of mitigation the County will pay for. The
Council can give guidance for the committee to hide behind when it has to say no.
Anderson stated none of them want to hide behind anything.
Nelson stated set a limit on the mitigation percentage for the advisory
committee, and anything greater would come to the Council for review.
Bronsema stated that sounds good.
Anderson stated he agrees with Councilmember Nelson's idea.
Hatch stated a lot of staff time goes into a project before coming to the
advisory committee for approval. The benefit of Councilmember Nelson's
suggestion is that staff will know ahead of time if they are getting into a higher
figure. The suggestion is a great approach.
Roll stated this is a great discussion on the topic of flood plain and salmon
integration, and allowing the two to coexist in a mutually beneficial way.
Surface Water Work Session, 10/18/2005, Page 13
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
Monsen stated they would like to get credit for restoration when they choose
to put it in.
Sediment Management Plan
Anderson stated he is the chair of the subcommittee. He referenced the Kerr
Wood Leidal report. This is not a final report. It is a work in progress. The cover
page says it is a final report.
They've talked with many agencies. One element that is missing is on the
meeting with the river gravel users, who are people who mined the river in the
past. They want to find out why they left and what it would take to get them
interested in getting back to river gravel mining. That attachment will be added to
the packet. Hopefully, they will come up with a Nooksack River Sediment
Management Plan. They all realize that the floor elevation of the river is rising.
They don't have capacity, so they have minor flood events.
Brenner asked if there will be an evaluation that was done on the other
rivers. According to what she read, it will take time to find out that they have no
net loss. She asked if they would also factor in the additional gravel since they
stopped scalping. Cooper stated there is a pilot project to compare a few river bars
with topographic mapping of the river. They've learned that the error in that
analysis would be too great for the agencies to grant a permit. In the spring, they
will do bathymetry for the river. That will provide the basis for more detailed
analysis with a small enough error that will allow the agencies to grant a permit.
Anderson stated the consultant, Kerr Wood Leidel, will be at the meeting on
the 27t"
Caskey- Schreiber stated the report also talks about other measures to deal
with if the river fills up. Look at overflow areas and widening certain meander
areas. She asked if they are looking at it. Bronsema stated they are looking at it.
Channel migration is an aspect of their work, as is the hydraulic model, which is to
scientifically identify if these ideas will work. In many ways, the plan is everybody's
best guess. Now they have to prove these things scientifically. The gravel is
making the river level higher. Identify an overflow area, put water out there, which
will lower water level downstream. The model will identify if it will be enough.
People live in overflow corridors and it will come down to a cost benefit.
Caskey- Schreiber stated she read that they recommend removing 200,000 to
400,000 cubic yards per year.
McShane asked if the Nooksack River is referred to as an alluvial fan.
Thompson stated it is an alluvial river, which is not the same as an alluvial fan.
McShane asked if they've come to any conclusions at all about whether it is
incising or aggrading. Cooper stated the document lays out what has been done
Surface Water Work Session, 10/18/2005, Page 14
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
and is a proposed approach for the agencies. They wanted to keep it scientific.
They tried to be unbiased going into this.
McShane asked how much it will cost. There are huge errors with what they
currently have. Cooper stated the bathymetry was approved for $400,000. She
hasn't come forward with a final proposal for the bathymetry project yet.
McShane stated they would have to come back and do it again in ten years,
before they have any idea whether or not there is aggradation on a temporary
basis. Cooper stated they are now doing a pilot study with the less accurate data
that will show some evidence that there is capacity limitations due to gravel bar
accumulation in some locations.
Monsen stated this is one of those areas where they believe it's worthwhile to
have a gravel extraction program. It may be one of those test cases where they
end up forcing, rather than somehow absolutely proving, no harm, is that they can't
study this forever, either.
Thompson stated one challenge inherent with this kind of work is the scale
on which they are working, such as a gravel bar or a longer reach of the river.
The committee and Council must struggle with that direction.
Polindar stated that in 1993 and 1994, when they did the Hannegan project
from Lynden to the Pole Road, they scalped two gravel bars. They took out
thousands of yards. After the flood of 1995, they were right back to where they
were before. Just one flood did that. The gravel is still coming. Capacity keeps
getting narrower. Overflows will help, but there will be a lot of contention about it.
He agrees with it, especially up toward Everson, but he doesn't know if it will
happen.
Nelson stated he has some questions about the information and what is
being used. He likes using science -based information to evaluate this. He read
from the summary of the lower Nooksack River approach. He asked if there won't
be carte blanche sediment management on the river, but pinpointing specific areas
and then doing an evaluation of sediment quantity and ecological impacts.
Anderson stated they all realize they aren't going to wholesale remove gravel
without the best science they can possibly have. He hopes the end product will
have areas defined where they can use. It may be a test model to begin with. It
seems they have to prove they are losing capacity. If that's what they have to do
to appease the agencies, they will do that.
McShane stated critical information is on page 2 -14 about sediment delivery
over time. The amount of aggradation at the Deming Bridge in about 6,000 years
is critical information. Nowhere is there information about whether or not the basin
is dropping. There is at least one fault line with differential movement across the
area below Deming. That's not a lot of aggradation in 6,000 years, if that data is
accurate.
Surface Water Work Session, 10/18/2005, Page 15
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
Polindar stated that from 1900 to the 1960's, all cement poured in northern
Whatcom County was from the Nooksack River. However, every time they have a
high water, the gravel bars were back and people could continue to scalp the gravel
bars. That went on for 65 years. Now, they'd think no gravel has come down since
the 1960's. That's crazy. The gravel bars are getting higher and the river bed is
getting higher. The sediment will continue to come until they do something about
it.
Anderson stated the advisory committee would like to come back and talk to
the Council again. This is a good discussion. The advisory committee needs to
better prepare the Council for these events. People will want to know what is
happening.
3. LAKE WHATCOM
Geneva Stormwater Update
Kirk Christensen, Stormwater Engineer Manager, stated there are three parts
to the Geneva work, including stormwater retrofits throughout this area to the
north of Cable Street, reconstruction of Cable Street, and a transportation traffic
study on moving the majority of the traffic from Lake Whatcom Boulevard to Austin
Street and Lake Louise roads.
The area is divided into sub - basins. He indicated the sub - basins on a map.
They are looking at alternatives for stormwater treatment, such as rain gardens,
bio- retention, and treatment vaults. He indicated the potential locations for those
treatments on a map. CH2M Hill has a model of low impact feasibility evaluation.
It will estimate how effective these treatments will be to reduce phosphorus,
metals, and other sediment loads in the lake.
Caskey- Schreiber asked if widening ditches is contrary to low impact
development (LID). Christensen stated it would create better treatment with the
right plans. They are like filter strips. They are also looking at installing some
vaults.
Roy asked if a vault releases the water gradually. Christensen stated a vault
would be for treatment. A filter cartridge treats the water better before it runs into
the lake. Detention isn't a huge concern in the Lake Whatcom watershed.
Nelson asked how a vault reacts during a storm event. Christensen stated
the vaults treat the water from the smaller events, which is more polluted. The
water is fresh off the pavement. The larger events are routed around the vault.
They assume the water is cleaner at that point because it is more diluted. The
smaller events scrub all the oils off the road first. That is what they're trying to
catch.
Surface Water Work Session, 10/18/2005, Page 16
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
They want to get a couple of the easier projects done next year. The
following year do more, in conjunction with the Cable Street construction.
Another aspect is routing the flows. Now, the flows go straight down Cable
Street, without much treatment. They're planning on rerouting the flows so there is
more treatment before entering the lake. They will install diversion structures at
various locations along Cable Street to change the natural flow path. It will result
in more effective treatment.
Roy asked about rerouting water past homes that have never had full ditches
before. Christensen stated they are rerouting the smaller events. The bigger
events will still go straight down Cable Street.
Roy asked if there is a community involvement piece. Christensen stated
there is, but they're not there yet.
Monsen stated the ditches will have to be maintained. They'll have to
educate the community about a changing landscape.
Brenner stated this is great. She asked if they are working with 20/20
Engineering or other private professionals who are familiar with this technology.
Christensen stated they will be using the same technology that the engineering
firms use.
McShane asked if they have some flexibility in terms of rights -of -way.
Christensen stated he is working on getting the rights -of -way organized.
McShane stated that might also be a public education piece.
Christensen stated another component is the construction of Cable Street.
They're going from Lake View to Lake Whatcom Boulevard. There are big
stormwater issues. There are sidewalks. There is road widening from 34 to 36
feet. They are going to look at low impact techniques to minimize the amount of
impervious surface and figure out how to adequately treat the stormwater. There is
an inadequate stormwater system going down Cable Street right now. It's a huge
problem.
Brenner asked if all this stuff will work well when they add the street width
by one - third, using impervious surface. Christensen stated they will improve the
strips by using low impact development.
Nelson asked if this is secondary to stormwater management and the sewer
system. He asked if this would be before it goes into the stormwater system, as if
it were pretreatment. Christensen stated it would be both. There would be
treatment before the runoff runs into the system, and there would be more
treatment down the line.
Surface Water Work Session, 10/18/2005, Page 17
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
Nelson stated they characterize this as treatments before major events.
When there is a major event, it goes down Cable Street and into the lake. During a
major event, the flow is higher. He asked how they keep it from going into the
treatment systems designed for smaller events. Christensen stated they can design
the control structures accordingly. They take a certain amount of flow out one way.
Anything above that goes down the main path. A small amount would still go into
the control structures, at an amount they can handle.
Another aspect is moving traffic from Lake Whatcom Boulevard to Austin
Street and Lake Louise Road. Now, they're hiring a consultant to do a study to look
at the situation, look at accidents, and look at travel times to figure out if it's
feasible to reroute the traffic.
Nelson stated they had talked at one time about traffic signalization to
change the traffic pattern at a certain location. He asked why that never happened.
People are looking for the route that saves the most time. If they install a traffic
signal, it will slow down the route so people will choose an alternate route.
Christensen stated the study will look at the options for traffic flows.
McShane asked if part of the reason for diverting traffic from the lower end of
Cable Street or along Lake Whatcom Boulevard is to provide more opportunities for
treatment facilities. Christensen stated that is a possibility.
McShane asked how important is the actual location of the traffic to
phosphorus loading. Christensen stated it is significant.
Roll stated there was a study a while back about the roadway pollutants.
They can bring that information back to the Council.
Brenner stated she would like to see that information. Fixing the problem by
creating more impervious surfaces goes against what she knows.
Caskey- Schreiber stated they will hear more about the Lake Louise Road
design as they develop the design to low impact development standards.
Monsen stated the design process for Lake Louise Road itself is related.
There has to be more discussion on the amount of money they should invest to
shift the route. Staff is planning to move ahead with rebuilding Lake Louise Road.
That will shift some traffic. How much more traffic they want to shift needs to be
discussed.
Roy stated she agreed that it's uncomfortable to talk about treating
stormwater going into the lake and also talk about widening the roads, which is one
of the things that they are told is a cause of the problem. Come back with real
facts that they can get away with widening the road and treating the runoff better
so the net result is less. Also, do pervious bike trails.
Surface Water Work Session, 10/18/2005, Page 18
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
Monsen stated they are now beginning to make ensure that low impact
development techniques in places where there will be a low impact use. Low
impact development in locations that have a high use make problems worse, not
better.
Nelson stated the use on Northshore Road isn't as high as they have on Lake
Louise Road or Lake Whatcom Boulevard. He asked if that is more of a safety
issue. Monsen stated Northshore Road is a safety issue. The reconstruction of
Lake Louise Road is heavily dominated by a safety issue. The reconstruction of a
Cable Street alignment is a combination of water quality, safety, urbanization.
Brenner stated they'd be better off by putting a deputy on the road, who
would more than pay for himself from the tickets. Also, do the bike paths and
sidewalks with porous concrete. She wants to see a significant reduction, not a
minimal reduction, with the money they are spending.
Nelson stated the safety issue isn't just speeding traffic. The safety issue is
also with the curves, lighting, bicyclists, and other things the Sheriff doesn't have
control over.
Roll stated staff will be going through an analysis of what a stormwater
manual adoption means in the context of phase two.
(Clerk's Note: End of tape two, side A.)
Roll continued to state that they may want to use certain pieces of the plan
in certain areas, or they may want to use the whole thing countywide. There will
have to be discussions with the Building Services Division to make sure they
understand the requirements for work loads and needed skills.
ADJOURN
The meeting adjourned at 12:20 p.m.
Jill Nixon, Minutes Transcription
The Council approved these minutes on November 22-, 2005.
ATTEST:
WHATCOM COUNTY COUNCIL
WHATCOM COUNTY, WASHINGTON
Surface Water Work Session, 10/18/2005, Page 19
DISCLAIMER: This document contains the Whatcom County Council or Committee
minutes, as approved. However, unless an attested signature page is attached, they
are not the final approved minutes.
1 Dana Brown - Davis, Council Clerk Laurie Caskey- Schreiber, Council Chair
Surface Water Work Session, 10/18/2005, Page 20