HomeMy WebLinkAboutres1990-078- WnATCOM COUNTY COUNCIL AGENDA BILL NO. 90 -410
SUBJECT.•
Engineering 01115190
! _ 1990
WHATCOM COUNTY
►, COUNCIL
Intersection Signalization - SR -539 at Axton Road.
ATTACHMENTS.
.1. Letter from County Engineer
2. Bid Tabulations
3. Project Cost breakdown Public Hearing Needed? Yes No /x/
4. Resolution
SUMMARY STATEMENT.-
This project will provide a fully actuated traffic signal at the SR -539-
Axton Road intersection, greatly enhancing traffic circulation in this
vicinity.
ORIGINATOR'S RECOMMENDED ACTION.•
Award of b i d to the low b i dder, WATERWORKS; :1:NC...
amount of $69,690.00
COMMITTEE ACTION (including dates):
COUNCIL ACTION (including dates):
11/27/90: Council passed
Related File Numbers: Ordinance or Resolution Number. • RF590 -78
INTRODUCED BY Consent
PROPOSED BY Public Works Department
DATE 11/27/90
RESOLUTION NO. 90 -78
ESTABLISHING COUNTY ROAD PROJECT NO. 99195
AND THE AWARD OF THE CONTRACT FOR
THE INTERSECTION SIGNALIZATION OF SR -539
AT AXTON ROAD
WHEREAS, this project is a part of the officially adopted 1990 Annual Road
Program in accordance with RCW 36.81.130 as Item No. 9.
NOW, THEREFORE, BE IT RESOLVED by the Whatcom County Council:
That CRP 99195 is formally established for the Intersection Signalization
of SR-539 at Axton Road.
The contract for this project is awarded to WATERWORKS, INC. in
the amount of their bid of $69,690.00 including taxes.
An appropriation from the officially adopted road fund budget and based on
the County Engineer's estimate is hereby made in the amounts and for the pur-
poses shown:
PURPOSE
AMOUNT OF APPROPRIATION
Consultant Fees $ 7,100.00
Construction 69,700.00
Construction Engineering, 4,200.00
Surveying and Misc. Contingency
TOTAL $81.000.00
BE IT FURTHER RESOLVED that the construction is to be accomplished by
contract in accordance with RCW 36.77.020 et seq.
PASSED this 27th day of November
ATTEST:
amona Reeves
Clerk of the Council
1990.
WHATCOM COUNTY COUNCIL
WHATCOM COUNTY, WASHINGTON