HomeMy WebLinkAboutres1998-046WHATCOM COUNTY COUNCIL AGENDA BILL
NO. 98 -297
CLEARANCES
Initial
Date
Date Received in Council Office
Agenda Date
Assigned to:
ri inator:
BGM
7115/98
7/28/98
Finance /Council
Division Head
/N
7-14-78
Dept Head
� 4fo�98
Prosecutor
PurchasingBudget:
Executive:
tea/
SUBJECT .•
Replacement of Wickersham Road Bridge No. 125 Over the Samish River
CRP 997013
ATTACHMENTS:
1. Agenda Bill 5. Contract Information Sheet
2. Resolution 6. Project Cost Breakdown
3. Letter to County Executive 7. Bid Tabulation
4. Approval of Contract Award Form 8. Low Bid Proposal
-
Related County Contract #:
Should Clerk schedule a hearing: NO/ X / YES / / Requested Date:
SUAWARYSTATEMENT.•
Distribution Request
Indicate those who should receive a copy after Council action.
The 1.998 Annual Construction Program has a project No. 13, the
replacement of Wickersham Road Bridge No. 125 Over the Samish.
.Giver
This project will be funded by Federal (BROS) and local funds.
Recommend establishment of CRP 997013 and approval of award of
Contract to the lowest bidder, One Way Construction Co. Inc., in the
Amount of contract to $259,150.00.
ADS FacilitiesAfauagement
ADS Finance
Brad Bennett
ADSHumau.Resources
ADS Info Services
Assessor
Auditor
Marge Osborn.
Cooperative Extension
District Court
Executive
Francine Kincaid
Health
Hearing Examiner
Jail
Juvenile ,
Parks
Planning
COUNCIL ACTION TAKEN.
1998 - 297 7/28/98: Approved by consent, 6 -0, Nelson absent Resolution
#98 -046
A
Prosecutor
Public Works
Dawn Pierce
Sheriff"
Superior Court
Treasurer
Other
Bruce Mills
Ordinance or
this item):
er ��
J: 4GENDA BILL.doc
SPONSORED BY: Consent
PROPOSED BY: Public Works - Engineering Div.
INTRODUCTION DATE: 7/28/98
1 RESOLUTION NO. 98046
2 ESTABLISHING COUNTY ROAD PROJECT NO. 997014
3 AND THE AWARD OF CONTRACT FOR REPLACEMENT OF
4 WICKERSHAM ROAD BRIDGE NO. 125 OVER THE SAMISH RIVER
5
6 WHEREAS, This project is included in the officially adopted 1998 Annual Road
7 Program as item number 13,
8
9 NOW, THEREFORE, BE IT RESOLVED by the Whatcom County Council that CRP
10 997014 is formally established for the Replacement of Wickersham Road Bridge No. 125 Over
11 The Samish River. The Contract for this project is awarded to One Way Construction Co. in
12 the amount of their low bid of $259,150.00
13 „.
14 An appropriation from the officially adopted Road fund budget and based .on the County. Road
15 Engineer's estimate is hereby made in the amounts and for the purposes shown:
16
17
PURPOSE
18
19
Preliminary Engineering
20
21
Right-of-Way Acquisition
22
23
SUBTOTAL
24
25
Construction
26
27
Construction Engineering
28
Testing & Contingencies
29
30 TOTAL
31
AMOUNT OF APPROPRIATION
$ 16,000.00
$ 0.00
$ 259.200.00
$ 26.500.00
$ 16000.00
32 BE IT FURTHER RESOLVED that the construction is to be accomplished by
33 Contract in accordance with RCW 36.77.0 10 et. seq.
34
35 APPROVED this 28 day of July , 1998.
36
37
38
39
40
41
42 Dana -Trown avis, o ncil Clerk
43
44 APPROVED AS TO FORM:
45
46 (Previously approved as to form
47 by Daniel Gibson on 04/10/98)
48 Civil Deputy Prosecuting Attorney
49
$ 301,700.00
WHATCOM COUNTY COUNCIL